Syed Qasir Raza
Power Plants
Kohat, Pakistan
Summary of Career
1. Presenting 12 years experience, within various legendary industries environment, including power plants, Cement industry, natural gas & marine industry.
2. Having experience operation and maintenance of Wartsila diesel/hfo & gas power plants.
3. Maintain and commissioning of gas pipelines in natural gas industry with SNGPL Company.
4. Use wide variety of reliability tools such as RCM programs to analyze equipment.
5. Having experience in marine industry as technician in dry docks world Dubai Company.
6. Having experience operation & maintenance of pumping station.
7. Erection and commissioning of cooling towers, pumps house and screw compressors.
8. Erection and commissioning of recycling, ultra filtration plant & reverse osmosis plant.
9. Having experience in Autocad drawings.
10. Coordinating office activities and operations to secure efficiency and compliance to company policies.
Experience as Service Mechanic Power Plants
Wartsila Pakistan Pvt Ltd
28 January 2010
27 March 2012
Major Service and Maintain Mechanical Equipment As per Job Order.
Worked as team member during major overhaul/ maintenance activity.
Performed the preventive and periodic maintenance of Wartsila engines, 11x18V46D at site Liberty Power Tech Faisalabad and Wartsila duel fuel engines, 2x18V50DF at site DG Cement Kallar Kahar.
Performed the maintenance of engines as 500 hrs, 1000 hrs, 2000 hrs, and 4000 hrs, Major maintenance 18000 hrs of 18V50DF & 12000 hrs of 18V46D.
Trouble shooting & routine maintenance of HFO and Lube oil separator of ALFA LAVAL.
Perform the maintenance of compressors, cooling towers, water and oil pumps and steam lines.
Performed the maintenance of oil bath filters, fuel module system.
Conversion of duel fuel engines, Gas to HFO & HFO to Gas
Prepared Technical reports and worked on Maintenance management reports.
Experience as Mechanical Technician
Drydocks World Dubai
27 March 2013
14 August 2013
Responsible maintenance, fault diagnosis and repair, Including systematic strip down and re-building of mechanical equipment and components to cranes, winches, Pumps, Compressors, Diesel Engines, Valves and other similar plant and equipment.
Installation of mechanical plant and equipment.
Execute of planned preventive maintenance tasks.
Responsible for safety and quality requirements all the time.
Performed other job related duties as assigned by the section head.
Ensure that the safety, quality & environment requirements of the yard are met.
Experience as Sub Engineer UFG-C
Sui Northern Gas Pipelines Limited
11 January 2013
04 April 2014
Working as a Sub Engineer (Operation & Distribution) and lead more than 100 supervisors, Fitters and helpers in Sui Northern Gas Pipeline, Ltd Pakistan.
Maintenance and Commissioning of gas pipeline/service lines and Industrial/Commercial & Domestic Gas meters.
Look after Operation/ Maintenance activities for SMS, CMS and Gas leakage activities.
To assist in UFG-C department to control gas theft.
Documentation for UFG Department.
To achieve special task as assign by head of department.
Data Downloading from All EVC`S And Putting Composition.
Experience as Pumping Station Operator
Saudi Services for ElectroMechanical
05 April 2014
07 July 2014
Performed testing and commissioning activity at Ras Alzaur Riyadh water Transmission System.
Responsible Working on water station plant (Ras Alzaur Riyadh water Transmission System Saudi). Plant capacity 900,000 m3/day.
Start –up, Shutdown and trouble shooting of the continuous process plant.
Executing and condition monitoring of process activities in the field.
Experience in operating DCS system (ABB)
Monitoring, Measurement and Control of process parameters, Trouble shooting, Reporting abnormalities.
Experience as Associate Engineer Mechanical
Maple Leaf Cement Factory Limited
12 January 2015
17 June 2017
Performed the preventive, corrective & breakdown maintenance of Wartsila Engine 18V50DF.
Performed the preventive, corrective & breakdown maintenance of NIIGATA Diesel Engines 18V32CLX as 1k, 3k, 6k running hours and 8k major maintenance.
Trouble shooting & routine maintenance of HFO and LO separators of ALFA LAVAL, Turbo charges, Compressors, Pumps, Cooling towers and different types of valves.
Response immediately to plant & equipment breakdown
Rise work Request / Orders to take Corrective/ Preventive action over processing equipment to correct defects found during inspections.
Used a wide variety of reliability tools such as RCFA, and RCM programs, to analyze equipment, and initiate best maintenance practices for enhanced operational reliability.
Check the vibration, Sound and temp of different motors, pumps & other rotating machinery.
Record the technical data of spare parts replacement and wear rate of machine parts with data entry operator to maintain the history of machine parts.
Response immediately to plant & equipment breakdown.
Notifying area In-charges and other personnel of maintenance problems, and assist in identifying and correcting these problems, with recommended Corrective / Preventive action.
Experience as Assistant Manager
Kohat Cement Company Limited
17 June 2017
04 February 2020
Regarding Plant:-
Maintain the care, custody, control and safe operation/maintenance of Power Plant (22MW). Wartsila Engines 18 V 38.
Implementation of the planned and preventive maintenance schedule and quality plan.
Develop and implement procedures and systems for plant personnel to operate in a safe and high performing manner.
Working as team leader during maintenance activities.
Responsible for all measurement/inspection of parts during maintenance.
Submit daily & monthly maintenance activity report to plant Manager.
Responsible for keeping the whole data recording of all maintenance activities.
Performed inspection of store spare parts received from import and local market.
Carryout training of fresh and newly joined maintenance staff
Attend regular follow-up/progress meetings with GM works
Worked on eAM Oracle based management system project.
Regarding Projects:-
Lead, Participate in project 7800 TPD Cement Plant and 18 MW Waste Heat Recovery Plant.
Managing the team for shipment handling of new Cement Factory.
Unpacked and examined incoming shipment, reported damaged item to GM Works and Insurance Company.
Installation of Fire Fighting, Raw water, Industrial water pipelines for 7800 TPD Cement Plant.
Erection & Commissioning of Cooling Tower, Pump House and Screw Air Compressors.
Erection and commissioning of Reverse Osmosis (Recycling) Plant with capacity 40 m3/Hours.
Erection & Commissioning work in progress of 18 MW Waste Heat Recovery Power Plants.
Bachelor 30 December 2009
Bachelor of Technology (B.Tech) in MechanicalIntermediate 31 May 2006
Diploma of Associate Engineer in Mechanical