Nimi
Dubai
Summary of Career
1. • Working as Sr. Planning and Controls Engineer under PMO,
2. • Preparation of baseline schedule
3. • Establishing a regular basis of updating the project schedule to ensure the timely reporting of schedule information.• Monitor effectiveness of Project controls procedures and reports to meet project needs, propose improvements and follow-up on implementation. . • Prepare schedule variance and cost variance matrix for internal review of Project Controls and Project director. • Prepare The Engineer’s review comments on the Contractor’s reports and confer compliance with th
4. Coordination with the Management to prepare various reports that meet Client requirements - Monthly Progress Reports, weekly reports etc.• Review of the Contractor’s schedule in Primavera-Three month rolling programme ,six month look ahead schedule and prepare the Engineer’s final review report for submission to RTA. • Analyze data via reports, graphics. • Disseminate / communicate updates via layouts/report using P3.
5. • Assessing actual progress versus planned progress to determine trends and variances. • Analysing schedule trends, determining risks and developing options for corrective action.
6. • Revising the project plan and project schedule) (re planning and recovery programmes) as required for Client approval.
7. • Assuring the credibility of the information contained in the schedule. • Assisting the preparation of project time and cost claims.
8. • Preparation of S-curve, manpower and equipment histograms. • Preparation of recovery programme. • Review, coordinate and comment on Contractor’s reports (Monthly reports, weekly reports) for contentious, contractual, technical deficiencies. • Review & update Management procedures as required, in consultation with Controls team. • Monitor effectiveness of project controls procedures and reports to meet project needs, propose improvements and follow-up on implementation.
9. • Generation of tabular and graphic reports from P6 as per project requirement. • Compilation of Monthly Progress Reports as per Client/Consultant requirements.
10. • Conduct and initiate what-if analysis on programmes to identify areas of opportunity and uncertainty and report / initiate required corrective actions. • Manage, collate, prepare and issue all Engineers project reports. • Formulating and analysing Key Performance Indicators (-KPI). • Formulate Earned Value analysis sheet.
Experience as PLANNING ENGINEER
08 December 1999
31 December 2001
DESIGNATION:- PLANNING ENGINEER
WORK AREA:- ABU DHABI
EMPLOYER AND CONTRACTOR: - M/S CEESCO
MAIN CONTRACTOR:- MABANI
PROJECT :- Contract No. ADSS 512/4 MAFRAQ SLUDGE MANAGEMENT AND ODOUR CONTROL (M&E WORKS)
CLIENT :- ABU DHABI MUNICIPALITY SEWERAGE PROJECTS COMMITTEE ,SPC
• Working as Planning Engineer 1999-2001
• Coordinate the formation of WBS and baseline schedule.
• Monitor the updates on critical activities and the progress of tasks in P3.
• Compare progress and costs to targets.
• Evaluate performance.
• Preparation of S-curve.
• Analyze data via reports, graphics.
• Disseminate / communicate updates via layouts/reports.
• Supervision of the updated actual progress and formulated earned value.
Experience as ENGINEERING CO-ORDINATOR
01 January 2002
31 December 2004
DESIGNATION:- ENGINEERING CO-ORDINATOR
WORK AREA:- ABU DHABI
EMPLOYER: - TECHNIP
PROJECT :- SOROOSH AND NOWROOZ INTEGRATED DEVELOPMENTAL PROJECT
CLIENT :- SHELL , NPCC
PROJECT :- SRU Project (KSA)
CLIENT :- SAUDI ARAMCO
• Working as Engineering Coordinator,2002-2004
• Technical collaboration from Vendor Control with local and foreign vendors.
• Co-ordination between several engineering departments.
• Preparing reports per submittal for circulation to each department.
• Follow-up with vendor for all requirements of the Engineering sector through Vendor
Control.
• Monitoring every stage of technical documents for final approval.
Experience as PARSONS INTERNATIONAL.LIMITED PROJECT: - DUBAI-METRO PROJECT
05 April 2006
20 November 2008
DESIGNATION: - PROGRAMME ASSURANCE REPORTING ENGINEER (PROJECT MANAGEMENT-PLANNING AND CONTROLS)
WORK AREA: - DUBAI
EMPLOYER & ENGINEER: -PARSONS INTERNATIONAL.LIMITED
PROJECT: - DUBAI-METRO PROJECT
CLIENT :- RTA-DUBAI GOVT.
ENGINEER:- SYSTRA - PARSONS JV
• Programme Assurance Reporting Engineer” under Project Planning and Controls Division at The Engineer’s (Consultant-Systra-Parsons JV) Office, for the Dubai Metro Project,2006-08.
• Coordination with the Management to prepare various reports that meet Client requirements - Monthly Progress Reports, weekly reports etc.
• Review of the Contractor’s schedule in Primavera-Three month rolling programme ,six month
look ahead schedule and prepare the Engineer’s final review report for submission to RTA.
• Analyze data via reports, graphics.
• Disseminate / communicate updates via layouts/report using P3.
• Monitor effectiveness of Project controls procedures and reports to meet project needs, propose improvements and follow-up on implementation. .
• Prepare schedule variance and cost variance matrix for internal review of Project Controls and
Project director.
• Prepare The Engineer’s review comments on the Contractor’s reports and confer compliance
with the General Specifications and the Particular Specifications.
• Review, coordinate and comment on Contractor’s reports (Monthly reports, weekly reports) for
contentious, contractual, technical deficiencies.
• Review & update Management procedures as required, in consultation with Controls team.
• Monitor effectiveness of project controls procedures and reports to meet project
needs, propose improvements and follow-up on implementation.
• Conduct and initiate what-if analysis on programmes to identify areas of
opportunity and uncertainty and report / initiate required corrective actions.
• Manage, collate, prepare and issue all Engineers project reports.
• Formulating and analysing Key Performance Indicators (-KPI).
• Formulate Earned Value analysis sheet.
Experience as PLANNING AND CONTROLS ENGINEER
01 December 2008
30 December 2010
DESIGNATION:- PLANNING AND CONTROLS ENGINEER
WORK AREA:- ABU DHABI
EMPLOYER & CONTRACTOR: - LINDENBERG EMIRATES LLC (LINDENBERG WATER AND DRAINAGE DIVISION)
PROJECT: - O-1047-SEWERAGE AND SURFACE DRAINAGE WORKS (SAS AL NAKHEEL-SEIH SHUHAIB)
CLIENT :- ADSSC(ABU DHABI SEWERAGE SERVICES COMPANY)
ENGINEER:- PARSONS I.L.
EMPLOYER & CONTRACTOR: - LINDENBERG EMIRATES LLC (LINDENBERG POWER DIVISION)
PROJECT: - D-7150–SECURITY & UPGRADING OF 11KV ELECTRICAL NETWORK FOR
H.H.SHK KHALIFAH PALACE IN ABUDHABI & ERECTION OF EQUIPMENT IN SUB STATION NO.4&5 IN BEACH PALACE
CLIENT :- ADDC(Abu Dhabi Power Projects Division)
ENGINEER:- OLP ENGINEERING CONSULTANCY L.L.C.
• Working as Planning and Controls Engineer ,2008-2010
• Preparation of base line schedule.
• Preparation of S-curve, manpower and equipment histograms.
• Preparation of recovery programme.
• Generation of tabular and graphic reports from P6 as per project requirement.
• Compilation of Monthly Progress Reports as per Client/Consultant requirements.
• Compilation of Weekly reports for Management review.
• Comparison of weekly and planned schedule.
• Updating the baseline schedule on weekly basis.
• Preparation of tender schedules.
• Also working as Divisional QHSE representative.
Experience as SR. PLANNING AND CONTROLS ENGINEER
01 February 2012
31 December 2013
DESIGNATION:- SR. PLANNING AND CONTROLS ENGINEER
WORK AREA:- ABUDHABI
EMPLOYER & ENGINEER: - ACE-ARAB CONSULTING ENGINEERS(2013 to 2014)
PROJECT : - DOT/C/MR/35/12 COMPLETION OF AL FALAH INTERCHANGE WORKS
CLIENT : - DEPARTMENT OF TRANSPORT,DOT, ABUDHABI
CONTRACTOR:-CHINA STATE CONSTRUCTION ENGINEERING CORPORATION MIDDLE EAST.
• Working as Sr. Planning and Controls Engineer under PMO,
• Preparation of baseline schedule.
• Establishing a regular basis of updating the project schedule to ensure the timely reporting of schedule information.
• Recording and assessing the effects of project schedule changes.
• Assessing actual progress versus planned progress to determine trends and variances.
• Analysing schedule trends, determining risks and developing options for corrective action.
• Revising the project plan and project schedule) (re planning and recovery programmes) as required for Client approval.
• Assuring the credibility of the information contained in the schedule.
• Assisting the preparation of project time and cost claims.
• Updating the baseline schedule on weekly basis.
Experience as SENIOR PLANNING ENGINEER
01 January 2014
PROJECT/WORK EXPERIENCE:
DESIGNATION :- SENIOR PLANNING ENGINEER
EMPLOYER & CONTRACTOR :- ETIHAAD EMIRATES MABANI TRANSPORTING AND GENERAL CONTRACTING COMPANY L.L.C. (JAN 2014 till date)
WORK AREA:- ABU DHABI
PROJECT : - ADSSC CONTRACT NO.O-11008(VO. #4) CONSTRUCTION OF NEW SEWERAGE NETWORK AT REEM ISLAND
PROJECT : - ADSSC CONTRACT NO.O-11008 ASSET ENHANCEMMENT SCHEME IN ABUDHABI AREA CONSTRUCTION OF DEEP TRUNK SEWER FROM MPS14 TO MPS 8 PROJECT INCLUDING INTERCEPTION OF SEWERS AND ABANDONMENT OF EXISTING PUMP STATIONS
CLIENT : - ABU DHABI SEWERAGE SERVICES COMPANY
ENGINEER ;- KN INTERNATIONAL ARCHITECTS AND ENGINEERS L.L.C
WORK AREA:- DUBAI
PROJECT : - SEWERAGE & DRAINAGE FOR LABOUR ACCOMODATION IN AL QUOZ INDUSTRIAL AREA-– DS127
CLIENT : - DUBAI MUNICIPALITY
ENGINEER ;- KHATIB AND ALAMI CONSULTANT
PROJECT : - MISCELLANEOUS WORKS AND HOUSE CONNECTIONS–DS 200
CLIENT : - DUBAI MUNICIPALITY
ENGINEER ;- MONTGOMERY WATSON HARZA (MWH) CONSULTANT
PROJECT : - AL MOHAISNAH 2NDSEWERAGE AND DRAINAGE FACILITIES (C264)- DS137
CLIENT : - DUBAI MUNICIPALITY
ENGINEER ;- ITAL CONSULT
PROJECT : - UPGRADING OF SUBSIDIARY SEWERAGE PUMPING STATION G1-G7 DS198/1
CLIENT : - DUBAI MUNICIPALITY
ENGINEER ;- ITAL CONSULT
PROJECT : - CONTRACT NO;DEWA-RFX# 2131400059 –NDRC WORKS-SUPPLY,INSTALLATION,TRSTING & COMMISSIONING OF GRE TRANSMISSION PIPELINE TO PROTECTDIVERT UNDER EXISTING SERVICES & ASSOCIATED WORK AT VARIOUS LOCATION IN THE EMIRATE OF DUBAI
CLIENT : - DUBAI ELECTRICITY AND WATER AUTHORITY
ENGINEER ;- NIPPON JOGESUIDO SEKKEI Co.Ltd
• Working as Senior Planning Engineer , under PMO,
• Establish baseline schedule
• Record progress of tasks in P6.
• Compare progress and costs to targets
• Evaluate performance.
• Preparation of S-curve.
• Analyze data via reports, graphics.
• Disseminate / communicate updates via layouts/reports.
• Formulate actual progress versus planned progress assessments.
• Update weekly and monthly reports
DESIGNATION:- SR. PLANNING AND CONTROLS ENGINEER
WORK AREA:- ABUDHABI
EMPLOYER & ENGINEER: - ACE-ARAB CONSULTING ENGINEERS(2013 to 2014)
PROJECT : - DOT/C/MR/35/12 COMPLETION OF AL FALAH INTERCHANGE WORKS
CLIENT : - DEPARTMENT OF TRANSPORT,DOT, ABUDHABI
CONTRACTOR:-CHINA STATE CONSTRUCTION ENGINEERING CORPORATION MIDDLE EAST.
• Working as Sr. Planning and Controls Engineer under PMO,
• Preparation of baseline schedule.
• Establishing a regular basis of updating the project schedule to ensure the timely reporting of schedule information.
• Recording and assessing the effects of project schedule changes.
• Assessing actual progress versus planned progress to determine trends and variances.
• Analysing schedule trends, determining risks and developing options for corrective action.
• Revising the project plan and project schedule) (re planning and recovery programmes) as required for Client approval.
• Assuring the credibility of the information contained in the schedule.
• Assisting the preparation of project time and cost claims.
• Updating the baseline schedule on weekly basis.
Bachelor 28 October 1999
• BACHELOR DEGREE IN ENGINEERING (1999) CHENGANNUR ENGINEERING COLLEGE, COCHIN UNIVERSITY OF SCIENCE AND TECHONOLOGY, KERALA, INDIAMaster 13 April 2017
• POST GRADUATE DIPLOMA IN CONSTRUCTION MANAGEMENT”- FROM THE INTERNATIONAL INSTITUTE OF MANAGEMENT AND TECHNICAL STUDIES, INDIA.Master 21 January 2007
• POST GRADUATE DIPLOMA IN TOTAL QUALITY MANAGEMENT-(JAN, 2007) - FROM THE INDIAN INSTITUTE OF MANAGEMENT AND TECHNOLOGY, INDIA.Master 27 February 2018
• POST GRADUATION DIPLOMA STRATEGIC PROJECT MANAGEMENT – (FEB2018)-FROM WESTFORD SCHOOL OF MANAGEMENT EDUQUAL, UK.Master 18 February 2010
• PROJECT MANAGEMENT - (FEB, 2010) - FROM FRANKLIN UNIVERSITY, COLUMBUS, OHIO, USA.Other 20 February 2010
• PRIMAVERA. 6.0 FEB 2010 • PRIMAVERA. 3.1 SEP 2007, REGIONAL EDUCATIONAL INSTITUTE, U.AE. • PRIMAVERA. 3 AUG 2001, REGIONAL EDUCATIONAL INSTITUTE, U.AE.Other 20 December 2018
• PMP (PROJECT MANAGEMENT PROFESSIONAL) FROM CHICAGO MANAGEMENT CONSULTANCY, PMI ACCREDITED INSTITUTE, U.AE. • PMBOK-5th EDITION 04-08-2017 TO 29-09-2017 • PMBOK-4th EDITION 27-02-2009 TO 22-5-2009