1. Result oriented E&I engineer having 10 years’ experience in the field of construction, operation/ maintenance of EPC and FSF (Field surface facilities) related activities in large infra structures / Oil & Gas industry .
2. Preparation of maintenance plans, activities, Schedules of MV and HV Level control panels, SF6 breakers, Transformers, Transmission lines, Switchgears, Isolators, RMUs, Auto reclosers, building management & control systems, solar power energy solutions and PLC Systems.
3. Extensive background in all phases of electrical systems, operation and power distribution of 11 to 66kv and LV systems.
4. Expertise in Plant operations, solving operational problems, determining project objectives.
5. Excellent quality control and testing skills including transformer turn ratio test (TTR), winding resistance test, transformer oil test, meggering and Hi pot test (AC+DC ) .
6. Responsible for the trouble shooting of underground cables, switchgears and overall transmission network & power distribution.
7. Estimation, preparation and assigning the resources such as manpower, materials, consumables and equipment tools required for all electrical and related works prior to execution.
8. Responsible for Installation, testing and commissioning of H T/ LT distribution, Control and Protection system of power plant.
9. Provided the technical expertise in the design and installation of the Electrical systems in the commercial and residential Projects.
10. Solar power schematic development, conceptualized design plans, preparation of detailed and accurate mechanical and electrical drawing sets for installation.
Experience as Electrical Engineer
China Petroleum Engineering & Construction Corporation (CPECC)
17 January 2012
04 January 2019
Extensive background in all phases of electrical systems, operation and power distribution of 11 to 66kv and LV systems.
Expertise in Plant operations, solving operational problems, determining project objectives.
Excellent quality control and testing skills including transformer turn ratio test (TTR), winding resistance test, transformer oil test, meggering and Hi pot test (AC+DC ) .
Implementing engineering standards, practices, and methods for operation & maintenance.
Upgrading existing electrical system utilization of the latest techniques and safety measures by implementing autoreclosers & protection schemes.
Responsible for the trouble shooting of underground cables, switchgears and overall transmission network & power distribution.
Estimation, preparation and assigning the resources such as manpower, materials, consumables and equipment tools required for all electrical and related works prior to execution.
Interpretation of construction drawings and studying the contract documents, applicable standards and specifications prior to execution of any job.
Managing and providing engineering and technical supports to all the electrical work groups at site.
Coordinating with Client / Consultant’s representatives for any site instructions and inspection of works.
Ensuring that the redline drawings, As built drawings, O&M Manuals and related documentation is prepared, reviewed, submitted and approved in a timely manner, in line with the contract
Summation of site daily reports, inspection requests, estimates and all applicable monitoring reports on regular basis or as required.
Ensures that all the works done are in accordance with the approved construction drawings, contract documents, project specifications and all applicable standards whether local, national or international standards.
Experience as Electrical Project Engineer
SKB Engineering and Construction Ltd
15 April 2010
20 December 2011
Worked as EPC engineer during installation of power plant, Transmission & distribution network of Shahbaz Air base infra-structure comprising of 100 distribution transformers, 10 Ring main units (RMU), 200 km (HV & LV) cables, building management and control systems.
Responsible for Installation, testing and commissioning of H T/ LT distribution, Control and Protection system of power plant.
Responsible for Installation of cable trays, ducts, conduits, bus tie ducts, earthing system, lighting protection system, indoor and external lighting systems, VFDs, batteries and UPS.
Installation ,testing, calibration and loop testing of field instruments such as flow level, temperature and pressure transmitters, gauges ,solenoid and pneumatic valves, control and on/off valves, limit switches, speed sensors etc.
Knowledge of low current systems including building management system.
Provided the technical expertise in the design and installation of the Electrical systems in the commercial and residential Projects.
Solar power schematic development, conceptualized design plans, preparation of detailed and accurate mechanical and electrical drawing sets for installation.
Prepare and presents Technical Reports, Progress Reports, Special Studies and assist in the preparation of the Cost Estimates.
Co-ordination of Electrical works with other trades on site.
Interpretation and understanding of BOQs. Drawings, Specifications & Tender Documents, Cost Estimation/Rate Analysis on BOQs
Instructed and coordinated closely with contractors for the implementation of quality assurance, plan, procedures and standards.
Monitoring site activities regarding quality inspections.
Ensuring that all work is as per specifications, Scope of work, drawings, procedures and method of statements to avoid/eliminate re-works for timely completion of project and on ward submission to PM.
Monitoring and mentioning problems of Electrical works during execution.
Monitoring the daily, weekly and monthly progress reports.
Experience as Maintenance Engineer
03 November 2008
15 April 2010
I had worked with EKL as Electrical Maintenance Engineer. My duties were to identify problems with the Equipment and Plant, work on repairs and maintenance. Obtain necessary supplies to perform preventive maintenance and repairs.
Preparation of planned and preventive maintenance schedules and their implementation at project sites.
Equipment inspection records and preparation / updating of equipment specification sheets and history files.
Preparation of budget for maintenance of all major equipment's.
Installation, operation and maintenance of Power generators, welding machines, ASD (Auto Star Delta) panels, ATS (Auto transfer switch) panels, miscellaneous Electrical equipment’s.
Responsible for carrying out quarterly audit of equipment at site to check the on ground implementation of equipment maintenance & operation systems.
Preparation of schedules and progress reports and submission to E&P Head.
Training of workshop personnel on enhancement of skills, the use of tools, and loss prevention through in-house arrangements of technical training & workshops.
Bachelor 01 October 2008