BENNET

ELECTRICAL ENGINEER
NAGERCOIL


Profile Views 253

Recommendations (0)

Skills
PROJECT EXECUTION FOR POWER PLANT/ OIL AND GAS PROJECTS.
  • Experience
    15
  • U.A.E Experience
    --
  • Industry
    Engineering
  • Nationality
    INDIAN
  • Visa status
    Not Applicable
  • Qualification
    Bachelor - ELECTRICAL AND ELECTRONICS ENGINEERING
  • Driving License: SAUDI ARABIA
Other Matching Titles/Position
Industry Titles
Engineering

Summary of Career

Work Experience (Employment History)

Experience as

  • Employer

  • From

    07 April 2008

  • To

    20 April 2009

  • Detail

    • Coordinating and directing sub-contractor with as built drawing for erection of cable conduits for running cable below grounding to transformer platform.
    • Organizing with a team of worker for cable routing to install conduit both for power cable and grounding cable while civil concrete is on progress.
    • Interaction with client for day to day work, to push the sub contractor for today’s target to meet the deadline and commitment for my scope of progress.
    • Involved in erection activity of MV/LV (11KV/400V) transformer, switchgear in my scope belongs to control building.
    • Coordinating with sub contractor supervisor to complete the work day by day basis in 1st floor Elevation erection of MV Switchgear-installation, alignment, busbar installation, panel rack internal wiring.
    • CT’s, VT’s and circuit breaker installation in MV switchgear was ruled under my scope.
    • Erection activity of 110DC switchgear, 110V battery charger, 120V UPS inverter, battery banks, grounding, cable laying, loop checking was done under my scope.
    • Entering to 2nd floor erection of DCS panel monitoring panel base alignment, equipment installation and preparing list of missing device in panel as per GA drawing will be rectified with concerned ABB supplier

Experience as

  • Employer

  • From

    04 January 2010

  • To

    25 April 2011

  • Detail

    • Handling the project in accordance with contract specifications, client instructions, work procedures, approved and GA drawings and method statements/Inspection test plan.
    • Responsible for field construction electrical operations within assigned areas.
    • Supervision for all start up erection activities of cable trays, cable trench, cable pulling and termination.
    • Responsible for planning and executing all site activities assigned related to commissioning of steam turbine/generator and ROP.
    • Perform erection work of 110KV/6.9KV/6.9KV station transformer with NGR including cable laying and termination.
    • Erection of MV/LV (6.9KV/480V) transformer’s capacity 2.5MVA, 2MVA and 1.6MVA.
    • Erection of MV Switchgear rating of 6.9KV and LV Switchgear rating of 480V.
    • Installation of 220V Battery banks, 220V DC Chargers, 120AC UPS and 24DC-DC converters.
    • Maintain daily routine inspection for proper cable termination, cable dressing, cable routing in MV and LV switchgear panel dully signed on record basis as per site progress schedule.
    • Monitor work activities and ensure all MV cables are properly terminated to all Cooling water Intake pumps.

Experience as

  • Employer

  • From

    04 October 2011

  • To

    18 April 2012

  • Detail

    • Plan accordingly to start erection activity of MV/LV 33/11.5KV/440V switchgear’s, bus duct, AC/DC UPS system, interposing relay panel and 800KVA EDG (LV emergency diesel generator).
    • Taking supervision for erection activity of panels and cable tray supports in SATELLITE INSTRUMENT SHELTER Building.
    • Prepared plan, evacuate all site activities related to precommissioning and power ON the equipment by leading my site team engineers/supervisor to ensure completion of work to be done as per schedule milestone.
    • Handling this project with accordance to engineering drawing and complete the work to fulfill the scope of full client’s satisfaction.

Experience as

  • Employer

  • From

    12 June 2012

  • To

    20 September 2013

  • Detail

    • Strong experience in field Supervision activity with effective planning to keep timeline schedule within budget for completion of project.
    • Act as primary technical coordination interface with client specific to project electrical systems to ensure that the client expectations are satisfied as scheduled commissioning for start up.
    • Ensure that projects confirm the clients approved basis of design and all applicable regulatory and code requirements for electrical equipment installations.
    • Responsible for the Electrical Scope to ensure the Contractor perform the work to agreed scope of work, specifications and Schedules all to an acceptable standard.

Experience as

  • Employer

  • From

    22 October 2013

  • To

    30 September 2016

  • Detail

    • Supervise the contractor and sub contractor personnel to ensure contractor performs all work to be done as per contract specification across design review, quality and technical management issues.
    • Manage and coordinate electrical engineering deliverables to ensure projects are executed in a safe, efficient, cost effective and timely manner for pre-commissioning till to start up for commercial operation.
    • Responsible for the project management of all electrical installations /execution of all Electrical Installation works associated with Equipment installation / Laying & Termination of Power/ Control / Signal cables / Grounding installation works / Cable tray / Conduit installation works

Academic Qualification

Bachelor 12 July 1993

ELECTRICAL AND ELECTRONICS ENGINEERING
Certifications
Recommend BENNET
Related UserList of Members
Mentor
Not yet Assigned
Profile Answers
Related Professionals
Profession: Architect
Current City: Abu dhabi

Profession: Agricultural/ Irrigation Engineer
Current City: Abu Dhabi

Profession: Mechanical engineer
Current City: Abu dubai

Profession: Material Inspector
Current City: Sheikhupura

Profession: Petrochemical Engineer
Current City: Dubai

Profession: Mechanical Engineer
Current City: Dubai