Senior Planning Engineer- Delay Analyst
Abu Dhabi
Summary of Career
1. 16 years experienced (15 years in UAE) Projects Planning & Control Professional
2. working as Delay Analyst & Senior Planning Engineer for ADNOC projects (with Hill International INc. as PMC)
3. ADNOC & Dubai Municipality approved, worked on several EPC Projects
4. Proficient in Planning , Controls, EOT , Dashboards
5. Proficient in Time Impact analysis
6. having excellent verbal and written communication skills (IELTS overall band score 8)
7. I had been working with the Contractors PMC consultant & Client side for projects valued more than 400 million AED which includes Hospital, Residential Towers, Research Centre for Khalifa University, Petrol Pumps for ADNOC , Bus depos for RTA, Warehouses, Labor accommodation etc
8. hands on experience in S-curves, Histograms, Progress Monitoring, Risk management
9. Keen learner and Team Player
10. • Review and continuously monitor, against approved project management baselines, the Contractor’s major construction progress and ensure equipment and manpower are adequate or in case of any shortage report to Engineering/Project Manager
Experience as Site Engineer
Adnan Asdar & Associates
01 February 2004
31 January 2005
PROJECT:
Pearl Continental (PC) Hotel, (four star hotel) Gwadar, Pakistan.
DESIGNATION:
Site Engineer
RESPONSIBILITIES:
• Supervised the Excavation work up to the desired structural level.
• To check and confirm the fixing of steel and formwork for Footings, Retaining walls, slabs, UGWT, Beams, Lift Walls and Columns etc.
• To check and ensure the quality of concrete for pouring.
Experience as Project & Planning Engineer
SOLANKI HOLDINGS
02 February 2005
28 February 2007
PROJECT:
1. Prepare baseline program for G+3P+HC+14 typical floors+ HP building for Sheikha Moza bint Zayed bin Sultan al Nahian in Al Nahda Sharjah and monitor the progress of project on regular basis through updating the schedule.
2. Prepare Master schedule of the works for the project G+3P+HC+17 Typical+HP on Primavera V3.1 and monitor the progress of project on regular basis through updating the schedule.
3. Prepare Master schedule of the works for the project G+3P+11 typical floors building on Primavera V3.1.
4. Prepare the Base line schedule of works for the project G+4P+15 typical floors on Primavera V3.1.
DESIGNATION:
Project Engineer
PROJECT:
G+3P+HC+14 typical floors+ HP building for Sheikha Moza bint Zayed bin Sultan al Nahian in Al Nahda Sharjah.
RESPONSIBILITIES:
• Allocating responsibilities to Supervisors, Foremen and charge hands.
• Quality control of workmanship and materials
• Prepare contractual claims as per FIDIC.
• Execution of all the Structural & Civil works strictly in compliance with the drawings and specifications.
• Coordination with MEP engineers.
• Prepare and certify the subcontractor’s bills and payments.
• Attending weekly and monthly coordination meetings.
• All incoming and outgoing correspondence with Client, Consultant and subcontractors.
• Provide necessary backups to the Project Manager.
• Prepare Progress Reports to update the Client and Consultant regarding the progress of the project.
Experience as Construction Manager
ABC building contracting
01 March 2007
14 September 2009
PROJECTS:
1. G+M+2 typical floor buildings (3buildings) warehouses (4numbers) and G+1 labor accommodation (1 building) (UAQ)
2. Office & logistic facility (10 warehouses) on plot no.598-1110 for Grand stores in Dubai investment park Dubai.
3. G+1 labor accommodation and warehouse at Sajjah
DESIGNATION:
Construction Manager
RESPONSIBILITIES:
• Supervising the execution of the project carrying out all activities in accordance with the contract requirement, quality plans, and appropriate inspection /testing plans, ensuring that all the resource such as manpower machinery equipment and materials are effectively utilized, monitoring and controlling all activities of personal including subcontractors at the project sites in line with project program and schedule.
• Being very familiar with Primavera (V 3 & 3.1), prepare Master schedule of the works identifying project activities in coordination with engineering, procurement, construction and commissioning departments.
• Monitor the progress of project on regular basis through updating the schedule.
• Ensure time & cost control of the project.
• Coordination with MEP engineers for the complex services like (Cold stores, BMS system, VESDA system, dock levelers & shelters, smoke ventilators etc).
• Liaison with the Client’s representative, Consultant, subcontractors and suppliers ensuring proper progress at site.
• Proficient in dealing with and responding to subcontractor variance reports and claims settlements.
• Preparation of all interim valuations (BOQ), method statements and shop drawing & material submittals for the approval of the consultant.
• To Prepare Monthly Progress Reports in order to update the Client and Consultant regarding the progress of the project
Experience as Senior Planning Engineer
Ali Mousa & Sons Holding
16 September 2009
14 April 2013
PROJECTS PLANNING:
1. Prepare Baseline schedule and weekly updating for proposed Construction of Bus service station at Al Khwaneej for RTA/PTP.
2. Weekly updating of construction program for Construction of Bus Depot at Jebel Ali for RTA/PTP.
3. Prepare Master program for proposed Construction of 14 filling stations for ADNOC distribution & regular monitoring through updates.
4. Prepare Clause-14 program for proposed Extension of Qassimiah Hospital Sharjah for Ministry of Public works & regular monitoring through updates
5. Prepare Master program for proposed Construction of KG+ Primary school @ Al Nouf sharjah for ministry of public works.
6. Prepare Master program for proposed Construction of 409 villas for Sheikh Zayed bin sultan housing scheme
RESPONSIBILITIES:
• Preparation of Master schedule of the works identifying project activities in coordination with engineering, procurement, construction and commissioning departments.
• Monitor the progress of project on regular basis through updating the schedule.
• Identifying and reporting potential critical activities to Project manager ensuring proper control for the progress.
• Progress analysis and productivity reporting, including histograms, S-curves and progress reports
• Possess good knowledge of FIDIC and prepare contractual claims accordingly.
• EOT claims preparation and delay analysis (using Time Impact analysis).
• Liaison with the Client’s representative, Consultant, subcontractors and suppliers ensuring proper progress at site.
• Methodological approach to scheduling with excellent attention to details.
• Attending weekly and monthly coordination meetings.
• Excellent written and verbal communication and correspondence skills.
Experience as Senior Planning Engineer
15 April 2013
31 December 2013
RESPONSIBILITIES:
• Overseeing the overall progress of all under construction & under design projects in complete coordination with Consultants and End-users.
• Preparation of department’s Yearly budget.
• Assist in manage department projects with compliance to PMI standards including the nine knowledge areas and throughout the five process groups.
• Monitoring the KPIs for the different stages of projects and Property management department’s functions.
• Identifying and reporting potential critical Risks to Department head ensuring proper control for the progress.
• Progress analysis and productivity reporting, including histograms, S-curves and progress reports
• Provide input to the department’s budget based cost estimate of new projects through verify and endorse payment certificates and monitor and analyze the projects budget utilization.
• Review & analysis of EOT & Cost claims contractual claims from Contractor.
• Liaison with the Consultant, contractors and suppliers ensuring proper progress at site.
• Providing Vital assistance to department‘s manager in project management domain.
• Assist in handling department’s communications with projects stakeholders including other departments or divisions.
Experience as Senior Planning Engineer- Delay Analyst for ADNOC Projects
Hill International, Inc.
05 February 2014
30 October 2019
PROJECTS
1. ADNOC Campus Development Phase 3 (South Lobby , Tunnel & External Works)
2. Refurbishment of ADNOC OLD HQ building & two building Blocks(block B &C).
3. Oil Spill Response Centre facility at Zirku Island (offshore).
4. Construction of PETROLEUM INSTITUTE RESEARCH CENTRE.
5. Design and Build of New Water Tankers Filling Station for ADDC in Abu Dhabi.
6. Design & build of Civil defense building at Sas al nakhl.
7. Reinstatement of Roads around ADNOC Schools at Sas Al Nakhl.
RESPONSIBILITIES:
• Review Contractors proposed site organization; Planners CV’s and report to the Engineering/Project Manager.
• Review and approve / comment on the Design schedules as submitted by the Contractor and ensure the Design Schedule is in compliance with the overall project schedule.
• Review and approve / comment on the procurement schedules as submitted by the Contractor and ensure the procurement schedules are in compliance and coordinated with current construction schedules.
• Review and continuously monitor, against approved project management baselines, the Contractor’s major construction progress and ensure equipment and manpower are adequate or in case of any shortage report to Engineering/Project Manager.
• Review in detail the recovery schedules/action plans as submitted by the Contractors and ensure manpower and site supervision staffs are allocated properly.
• Regular visits to project sites to validate whether the progress of work on site is in compliance with approved schedules, major milestones have been met and report deficiencies to Project Manager.
• Review all daily, weekly and monthly reports as submitted by Contractor and report to Project Manager any deficiency or non-compliance.
• Review EOT claim (delay analysis/Time impact analysis) in line with Contract provisions and report assessment to project Manager for EOT Entitlement.
• Review field design changes and Trend Notices and assess time impact, if any.
• Advise the Project Manager of any foreseen slippage of progress and corrective actions to be taken.
• Attend weekly progress meeting and monthly Executive meetings and participate in preparing the agenda.
• Assist Engineer/Construction Managers during preparation of Monthly Progress reports and Monthly Executive Presentations.
• Reviews the commissioning plans as submitted by Contractor and ensure its compliance with the approved construction schedule.
• Participate with PMC staff in reviewing the Close Out Reports as submitted by Contractors.
• Identify the potential risks (RISK REGISTER) & ensure the implementation of RISK MANAGEMENT according to the PMI Standards & ADNOC standard procedures.
Bachelor 31 December 2013
BE Civil Engineering